Friday, May 4, 2018

Critical Facilities & Data Center Design Consideration: Generator Systems Design (1)

Let's recap the basic concept of mission-critical facilities:-

(1) Uptime Four-Tier Levels
(2) Critical Supply Diagrams and Configurations

The terms “N, N+1 and 2N”, typically refer to the number of power supply and cooling components that comprise the entire data center infrastructure systems. An “N” system is not redundant at all. N+1 and 2N, represent increasing levels of component redundancies and power paths, roughly mapping to the Tiers 2-4.




A paralleled generator system uses two or multiple generators to form a large-capacity generator system. Paralleling multiple generators is achieved by synchronizing the output of the generators and connecting them to a paralleling switchgear (PSG) common bus. Synchronizing the output of the generators requires all of the paralleled generators to have the same voltage, frequency, and phase rotation.

With closed transition back to the utility, PSG will parallel the generators and synchronize the generator output with the utility source for a short duration before transitioning back to utility power. When connecting the generators in parallel or synchronizing with the utility, the following criteria must be met:

  • Matched / proper frequency
  • Matched / correct phase rotation
  • Phase voltages in phase and within specified voltage range

Typical parameters that determine synchronization include a voltage difference of less than 5%, a frequency difference of less than 0.2 Hz, and a maximum phase angle of 5 electrical degrees between the sources.

Closed transition is used when it is desirable to transfer loads with zero interruption of power when conditions permit. It is used when the generator system transfers back to the utility and when load testing the generators with building loads. Closed transition can be either a soft load transfer or a make-before-break transfer. The PSG soft-load transfer synchronizes and operates the generators in parallel with the utility and transfers loads in increments between the two sources, thereby minimizing voltage or frequency transients on the generator plant and utility distribution system.




The typical soft-load-transfer overlap time is around 2 seconds. The make-before-break transfer will parallel the generators and perform a transfer of load from the generator to the utility. This can be the transfer of one large block load or the transfer of multiple block loads having time delays between the block loads. Time-delay transfer can either be programmed through the PSG or the downstream automatic transfer switches (ATS). Typical ATS make-before-break transition overlap time is usually less than 100 milliseconds.


To simplify the design of a paralleled generator system, identical generators should be used with the same manufacturer, ratings, type, output rating and alternator pitch.

If paralleling of dissimilar generators is required because of existing onsite conditions, the design of a paralleled generator system becomes much more complex. Each generator configuration must be evaluated and dissimilar components, such as speed control, voltage regulation, and alternator, must be retrofitted to match.

"Pitch" is the term used to define the mechanical design characteristics of the alternator. Paralleling a generator of 2/3-pitch alternator design with a generator of 5/6-pitch alternator design will result in circulating neutral currents. The circulating current will be disruptive to protective device operation and may damage alternators.


Configurations


The electrical loads must be classified into emergency loads, required standby loads, and/or optional standby loads that classified loads are separated, and the generator sets are sized so one generator can serve the emergency and required loads purpose.(see the following Figures)



One generator supplies emergency power to emergency loads, required standby loads and optional standby loads.

Multiple generators in parallel supply power to emergency loads,  required standby loads and optional standby loads.


Kindly note paralleled generator systems that rely on a single master control for signals to start and close to a paralleled bus actually replace one failure point with two, as the master control and the communication link between the master control and the generator systems each represent Single Points of Failure. A well-engineered paralleling system will have dual hot-backup control systems, redundant communication pathways, redundant best battery select dc power supplies, multiple breakers, multiple power pathways, and a well-documented procedure for system recovery whenever a component fails.


Benefits of Parallel Generator Systems


Paralleling multiple sources provides increased reliability, flexibility in load management, and maintenance capabilities with little to no disruption. Multiple generators paralleled to a common bus can better serve emergency and business critical loads, particularly for system response time and dynamic load response once in operation. However, more complex, parallel generator standby systems have significant advantages with respect to reliability and redundancy. These advantages include redundancy, efficiency and ease of maintenance and serviceability.

Redundancy: 

The redundancy inherent in the parallel operation of multiple generators provides greater reliability than a single generator unit for critical loads. If an N+1 configuration is adopted, one generator can be offline for maintenance while serving the required loads. Furthermore, providing a running spare, an N+1 generator configuration will increase the reliability of the generator system from 98% to 99.96% reliability.

Efficiency: 

Variations in power demand can cause a single larger generator to run at loads of less than 30% of capacity. The optimum operational point is between 75% and 80% of its rated value. The paralleling control system can be equipped with a generator load control that can add and remove generators in response to the actual load/demand of the system. If the load changes and demand reach 90% of running capacity, for example, an additional generator can be started, synchronized, and paralleled to the bus with no time delay.

Maintenance and Serviceability:

Maintenance can be performed without interrupting the availability of the generator system because one generator can be removed from the system to undergo scheduled or unplanned maintenance while the other generators are available to supply the loads.



Go to the next articles:
Generator Systems Design (2) - Generator Ratings
Generator Systems Design (3) - Generator Sizing


About us

Strategic Media Asia (SMA) is one of the approved CPD course providers of the Chartered Institution of Building Services Engineers (CIBSE) UK. The team exists to provide an interactive environment and opportunities for members of ICT industry and facilities' engineers to exchange professional views and experience.

SMA connects IT, Facilities and Design. For the other design considerations, please visit 
(13) Generator Systems, etc.

All topics focus on key components and provide technical advice and recommendations for designing a data center and critical facilities.


Wednesday, May 2, 2018

Learn How to Design Electrical Systems for Mission-Critical Infrastructure (14 - 15 June 2018)



RELIABILITY & REDUNDANCY MATTER - Your facilities and IT infrastructure are complex that are different from general buildings and require special design and operation knowledge and skill. Understanding the design considerations and avoiding costly downtime are critical.

Subscribe to our Knowledge Blog (http://green-data.blogspot.com or http://data-center-design.tumblr.com), share your view and get monthly readings online. All topics focus on key components and considerations of designing / operating mission-critical facilities and infrastructure:-


(12) Electrical Rooms, etc.





Course in Electrical Design for Mission Critical Supply (2-day)
(14 - 15 June 2018, approved CPD course by CIBSE UK)


Mission critical facilities have particular power requirements that significantly impact how they are designed and operated. You will gain insight into the critical supply system, from power components to distributions and efficiency; from power requirements to sizing, design, testing and commissioning:-


-- Concept on primary supply and secondary supply
-- Power flow in mission critical supply system
-- Features of major equipment for critical supply

    > Uninterrupted power supply and power storage
    > Backup generator
    > Automatic transfer switch
    > Static transfer switch
    > Isolation transformer

-- Efficiency assessment
-- Power quality review
-- Configuration diagram of critical supply (N+1 / 2N) design & analysis
-- Review of cable sizing to incorporate harmonics content
-- Earthing system design
-- Testing and commissioning requirements
-- Brief of Systems Merging Appraisal Test (SMAT)


The course details about the power system components that support typical data centers or mission-critical infrastructure. It prepares individual to fully understand the high voltage systems' design & build by exploring the international best practices and the instructors' experience.

All sections are conducted by Chartered Engineers (CEng) who have more than 20 years experience in electrical engineering, project management, sustainable engineering and facility engineering for critical services.


Date: 14 - 15 June 2018 (Thursday - Friday)
Time: 10:00 – 17:30
Venue: 19/F, New Victory House (Officeplus), 103 - 93 Wing Lok Street, Sheung Wan, Hong Kong
(Near Exit A2, Sheung Wan Station)

Fee: Special rate for CIBSE / HKIE all membership classes

For course details, please refer to http://www.stmedia-asia.com/newsletter_6.html.



Enrollment & Registration

Kindly complete and return an Application Form together with a crossed cheque made payable to “Strategic Media Asia Limited” - Room 403, 4th Floor, Dominion Centre, 43 - 59 Queen's Road East, Hong Kong.


About the Organizer

Strategic Media Asia Limited (SMA) is one of the approved CPD course providers of the Chartered Institution of Building Services Engineers (CIBSE). Our mission is to provide an interactive environment and opportunities for the engineers to exchange professional views and experience on critical infrastructure and data center services.

SMA connects IT, Facilities and Design. For details, please visit www.stmedia-asia.com/about.html.


Adverse Weather Arrangement - Events in the morning, afternoon or evening will be cancelled if typhoon signal No. 8 or above or black rainstorm warning is still hoisted after (or is announced by the Hong Kong Observatory to be hoisted at / after) 6:00 a.m., 11:00 a.m. and 4:00 p.m. respectively. Delegates will be notified when the class will be made up as soon as possible.



P.S. Think your team might also be interested? Pass it on >

Strategic Media Asia Limited
Connecting IT, Facilities and Design

T (852) 2117 3893 | F (852) 2184 9978

Room 403, 4th Floor, Dominion Centre, 43 - 59 Queen's Road East, Hong Kong
http://www.stmedia-asia.com | http://green-data.blogspot.com